@@ -52,37 +52,37 @@ def assign_lag_time(
# Let's imagine we are creating a construction schedule. All tasks
# need to be part of a work schedule.
schedule = ifcopenshell.api.run("sequence.add_work_schedule", model, name="Construction Schedule A")
schedule = ifcopenshell.api.sequence.add_work_schedule(model, name="Construction Schedule A")
# Let's imagine a root construction task
construction = ifcopenshell.api.run("sequence.add_task", model,
construction = ifcopenshell.api.sequence.add_task(model,
work_schedule=schedule, name="Construction", identification="C")
# Let's imagine we're doing a typically formwork, reinforcement,
# pour sequence. Let's start with the formwork. It'll take us 2
# days.
formwork = ifcopenshell.api.run("sequence.add_task", model,
formwork = ifcopenshell.api.sequence.add_task(model,
parent_task=construction, name="Formwork", identification="C.1")
time = ifcopenshell.api.run("sequence.add_task_time", model, task=formwork)
ifcopenshell.api.run("sequence.edit_task_time", model,
time = ifcopenshell.api.sequence.add_task_time(model, task=formwork)
ifcopenshell.api.sequence.edit_task_time(model,
task_time=time, attributes={"ScheduleStart": "2000-01-01", "ScheduleDuration": "P2D"})
# Now let's do the reinforcement. It'll take us another 2 days.
reinforcement = ifcopenshell.api.run("sequence.add_task", model,
reinforcement = ifcopenshell.api.sequence.add_task(model,
parent_task=construction, name="Reinforcement", identification="C.2")
time = ifcopenshell.api.run("sequence.add_task_time", model, task=reinforcement)
ifcopenshell.api.run("sequence.edit_task_time", model,
time = ifcopenshell.api.sequence.add_task_time(model, task=reinforcement)
ifcopenshell.api.sequence.edit_task_time(model,
task_time=time, attributes={"ScheduleStart": "2000-01-01", "ScheduleDuration": "P2D"})
# Now let's say the formwork must finish before the reinforcement
# can start. This is a typical finish to start relationship (FS).
sequence = ifcopenshell.api.run("sequence.assign_sequence", model,
sequence = ifcopenshell.api.sequence.assign_sequence(model,
relating_process=formwork, related_process=reinforcement)
# Now typically there would be no lag time between formwork and
# reinforcement, but let's pretend that we had to allow 1 day gap
# for whatever reason.
ifcopenshell.api.run("sequence.assign_lag_time", model, rel_sequence=sequence, lag_value="P1D")
ifcopenshell.api.sequence.assign_lag_time(model, rel_sequence=sequence, lag_value="P1D")
"""
settings = {
"rel_sequence": rel_sequence,