Assign / unassign sequence should be specific to sequence type
I previously incorrectly believed that sequence types are mutually exclusive. E.g. you can have max 1 relationship between two tasks. Now after looking at more schedules I realise it's logically allowed to have more than one sequence relationship. For example simultaneous SS + FF.
This commit is contained in:
@@ -106,8 +106,16 @@ def assign_sequence(
|
||||
# to be 2000-01-05.
|
||||
ifcopenshell.api.sequence.cascade_schedule(model, task=formwork)
|
||||
"""
|
||||
# Matched on the type as well as the pair. Two tasks may legitimately be
|
||||
# sequenced more than once with different types — the classic case is a
|
||||
# "ladder", where a start to start lets the follower begin once the leader
|
||||
# has begun and a finish to finish stops it ending before the leader ends.
|
||||
# Both constraints are real and neither implies the other, so matching on
|
||||
# the pair alone silently hands back the wrong relationship: a caller adding
|
||||
# a second sequence would instead be handed the first, and editing the type
|
||||
# on it would destroy the constraint that was already there.
|
||||
for rel in related_process.IsSuccessorFrom or []:
|
||||
if rel.RelatingProcess == relating_process:
|
||||
if rel.RelatingProcess == relating_process and rel.SequenceType == sequence_type:
|
||||
return rel
|
||||
rel = file.create_entity(
|
||||
"IfcRelSequence",
|
||||
|
||||