See #6570. Tests for import cost schedule from csv and minor fix

This commit is contained in:
Massimo Fabbro
2026-01-23 11:01:50 +01:00
committed by Massimo Fabbro
parent f0b5ab860f
commit 714105b9fd
10 changed files with 106 additions and 1 deletions
@@ -0,0 +1,14 @@
Index,Identification,Name,Unit,Value,Quantity,Query,Property,Formula
1,E.01,Walls,m3,,,,,
2,E.01.01,Ground floor walls,m3,100,,"IfcWall, location=""Ground Floor""",GrossVolume,
2,E.01.02,First floor walls,m3,200,,"IfcWall, location=""First Floor""",GrossVolume,
1,A.02,Paintings,m2,,,,,
2,A.03,Paintings with water,m2,,,,,
3,B.05,White paintings,m2,25,,IfcWall,GrossVolume,
3,B.06,Colored paintings,m2,32,33,,,
3,B.07,Double paintings,m,,,IfcWall,,NetSideArea*2
2,C-01,Paintings with machine,m2,17,133,,,
2,C-02,Decorated paintings,m2,40,8,,,
1,D,Reinforcements,,,,,,
2,D.1,Walls reinforcements weight,kg,,,IfcWall,,Pset_ConcreteElementGeneral.ReinforcementVolumeRatio * GrossVolume
2,D.2,Beams reinforcements weight,kg,,,,,
1 Index Identification Name Unit Value Quantity Query Property Formula
2 1 E.01 Walls m3
3 2 E.01.01 Ground floor walls m3 100 IfcWall, location="Ground Floor" GrossVolume
4 2 E.01.02 First floor walls m3 200 IfcWall, location="First Floor" GrossVolume
5 1 A.02 Paintings m2
6 2 A.03 Paintings with water m2
7 3 B.05 White paintings m2 25 IfcWall GrossVolume
8 3 B.06 Colored paintings m2 32 33
9 3 B.07 Double paintings m IfcWall NetSideArea*2
10 2 C-01 Paintings with machine m2 17 133
11 2 C-02 Decorated paintings m2 40 8
12 1 D Reinforcements
13 2 D.1 Walls reinforcements weight kg IfcWall Pset_ConcreteElementGeneral.ReinforcementVolumeRatio * GrossVolume
14 2 D.2 Beams reinforcements weight kg