@@ -6,17 +6,376 @@ Scenario: Add cost schedule
When I press "bim.add_cost_schedule"
Then nothing happens
Scenario: Enable editing cost schedule
Given an empty IFC project
And I press "bim.add_cost_schedule"
And the variable "cost_schedule" is "{ifc}.by_type('IfcCostSchedule')[0].id()"
When I press "bim.enable_editing_cost_schedule(cost_schedule={cost_schedule})"
Then nothing happens
Scenario: Disable editing cost schedule
Given an empty IFC project
And I press "bim.add_cost_schedule"
And the variable "cost_schedule" is "{ifc}.by_type('IfcCostSchedule')[0].id()"
And I press "bim.enable_editing_cost_schedule(cost_schedule={cost_schedule})"
When I press "bim.disable_editing_cost_schedule"
Then nothing happens
Scenario: Edit cost schedule
Given an empty IFC project
And I press "bim.add_cost_schedule"
And the variable "cost_schedule" is "{ifc}.by_type('IfcCostSchedule')[0].id()"
And I press "bim.enable_editing_cost_schedule(cost_schedule={cost_schedule})"
When I press "bim.edit_cost_schedule"
Then nothing happens
Scenario: Remove cost schedule
Given an empty IFC project
And I press "bim.add_cost_schedule"
And the variable "cost_schedule" is "{ifc}.by_type('IfcCostSchedule')[0].id()"
When I press "bim.remove_cost_schedule(cost_schedule={cost_schedule})"
Then nothing happens
Scenario: Enable editing cost items
Given an empty IFC project
When I press "bim.add_cost_schedule"
And I press "bim.add_cost_schedule"
And the variable "cost_schedule" is "{ifc}.by_type('IfcCostSchedule')[0].id()"
When I press "bim.enable_editing_cost_items(cost_schedule={cost_schedule})"
Then nothing happens
Scenario: Disable editing cost schedule - after editing items
Given an empty IFC project
And I press "bim.add_cost_schedule"
And the variable "cost_schedule" is "{ifc}.by_type('IfcCostSchedule')[0].id()"
And I press "bim.enable_editing_cost_items(cost_schedule={cost_schedule})"
When I press "bim.disable_editing_cost_schedule"
Then nothing happens
Scenario: Add summary cost item
Given an empty IFC project
When I press "bim.add_cost_schedule"
And I press "bim.add_cost_schedule"
And the variable "cost_schedule" is "{ifc}.by_type('IfcCostSchedule')[0].id()"
And I press "bim.enable_editing_cost_items(cost_schedule={cost_schedule})"
When I press "bim.add_summary_cost_item(cost_schedule={cost_schedule})"
Then nothing happens
Scenario: Remove cost item
Given an empty IFC project
And I press "bim.add_cost_schedule"
And the variable "cost_schedule" is "{ifc}.by_type('IfcCostSchedule')[0].id()"
And I press "bim.enable_editing_cost_items(cost_schedule={cost_schedule})"
And I press "bim.add_summary_cost_item(cost_schedule={cost_schedule})"
And the variable "cost_item" is "{ifc}.by_type('IfcCostItem')[0].id()"
When I press "bim.remove_cost_item(cost_item={cost_item})"
Then nothing happens
Scenario: Enable editing cost item
Given an empty IFC project
And I press "bim.add_cost_schedule"
And the variable "cost_schedule" is "{ifc}.by_type('IfcCostSchedule')[0].id()"
And I press "bim.enable_editing_cost_items(cost_schedule={cost_schedule})"
And I press "bim.add_summary_cost_item(cost_schedule={cost_schedule})"
And the variable "cost_item" is "{ifc}.by_type('IfcCostItem')[0].id()"
When I press "bim.enable_editing_cost_item(cost_item={cost_item})"
Then nothing happens
Scenario: Disable editing cost item
Given an empty IFC project
And I press "bim.add_cost_schedule"
And the variable "cost_schedule" is "{ifc}.by_type('IfcCostSchedule')[0].id()"
And I press "bim.enable_editing_cost_items(cost_schedule={cost_schedule})"
And I press "bim.add_summary_cost_item(cost_schedule={cost_schedule})"
And the variable "cost_item" is "{ifc}.by_type('IfcCostItem')[0].id()"
And I press "bim.enable_editing_cost_item(cost_item={cost_item})"
When I press "bim.disable_editing_cost_item"
Then nothing happens
Scenario: Edit cost item
Given an empty IFC project
And I press "bim.add_cost_schedule"
And the variable "cost_schedule" is "{ifc}.by_type('IfcCostSchedule')[0].id()"
And I press "bim.enable_editing_cost_items(cost_schedule={cost_schedule})"
And I press "bim.add_summary_cost_item(cost_schedule={cost_schedule})"
And the variable "cost_item" is "{ifc}.by_type('IfcCostItem')[0].id()"
And I press "bim.enable_editing_cost_item(cost_item={cost_item})"
When I press "bim.edit_cost_item"
Then nothing happens
Scenario: Add cost item
Given an empty IFC project
And I press "bim.add_cost_schedule"
And the variable "cost_schedule" is "{ifc}.by_type('IfcCostSchedule')[0].id()"
And I press "bim.enable_editing_cost_items(cost_schedule={cost_schedule})"
And I press "bim.add_summary_cost_item(cost_schedule={cost_schedule})"
And the variable "cost_item" is "{ifc}.by_type('IfcCostItem')[0].id()"
When I press "bim.add_cost_item(cost_item={cost_item})"
Then nothing happens
Scenario: Enable editing cost item quantities
Given an empty IFC project
And I press "bim.add_cost_schedule"
And the variable "cost_schedule" is "{ifc}.by_type('IfcCostSchedule')[0].id()"
And I press "bim.enable_editing_cost_items(cost_schedule={cost_schedule})"
And I press "bim.add_summary_cost_item(cost_schedule={cost_schedule})"
And the variable "cost_item" is "{ifc}.by_type('IfcCostItem')[0].id()"
When I press "bim.enable_editing_cost_item_quantities(cost_item={cost_item})"
Then nothing happens
Scenario: Add cost item quantity
Given an empty IFC project
And I press "bim.add_cost_schedule"
And the variable "cost_schedule" is "{ifc}.by_type('IfcCostSchedule')[0].id()"
And I press "bim.enable_editing_cost_items(cost_schedule={cost_schedule})"
And I press "bim.add_summary_cost_item(cost_schedule={cost_schedule})"
And the variable "cost_item" is "{ifc}.by_type('IfcCostItem')[0].id()"
And I press "bim.enable_editing_cost_item_quantities(cost_item={cost_item})"
When I press "bim.add_cost_item_quantity(cost_item={cost_item}, ifc_class='IfcQuantityArea')"
Then nothing happens
Scenario: Remove cost item quantity
Given an empty IFC project
And I press "bim.add_cost_schedule"
And the variable "cost_schedule" is "{ifc}.by_type('IfcCostSchedule')[0].id()"
And I press "bim.enable_editing_cost_items(cost_schedule={cost_schedule})"
And I press "bim.add_summary_cost_item(cost_schedule={cost_schedule})"
And the variable "cost_item" is "{ifc}.by_type('IfcCostItem')[0].id()"
And I press "bim.enable_editing_cost_item_quantities(cost_item={cost_item})"
And I press "bim.add_cost_item_quantity(cost_item={cost_item}, ifc_class='IfcQuantityArea')"
And the variable "quantity" is "{ifc}.by_type('IfcQuantityArea')[0].id()"
When I press "bim.remove_cost_item_quantity(cost_item={cost_item}, physical_quantity={quantity})"
Then nothing happens
Scenario: Enable editing cost item quantity
Given an empty IFC project
And I press "bim.add_cost_schedule"
And the variable "cost_schedule" is "{ifc}.by_type('IfcCostSchedule')[0].id()"
And I press "bim.enable_editing_cost_items(cost_schedule={cost_schedule})"
And I press "bim.add_summary_cost_item(cost_schedule={cost_schedule})"
And the variable "cost_item" is "{ifc}.by_type('IfcCostItem')[0].id()"
And I press "bim.enable_editing_cost_item_quantities(cost_item={cost_item})"
And I press "bim.add_cost_item_quantity(cost_item={cost_item}, ifc_class='IfcQuantityArea')"
And the variable "quantity" is "{ifc}.by_type('IfcQuantityArea')[0].id()"
When I press "bim.enable_editing_cost_item_quantity(physical_quantity={quantity})"
Then nothing happens
Scenario: Disable editing cost item quantity
Given an empty IFC project
And I press "bim.add_cost_schedule"
And the variable "cost_schedule" is "{ifc}.by_type('IfcCostSchedule')[0].id()"
And I press "bim.enable_editing_cost_items(cost_schedule={cost_schedule})"
And I press "bim.add_summary_cost_item(cost_schedule={cost_schedule})"
And the variable "cost_item" is "{ifc}.by_type('IfcCostItem')[0].id()"
And I press "bim.enable_editing_cost_item_quantities(cost_item={cost_item})"
And I press "bim.add_cost_item_quantity(cost_item={cost_item}, ifc_class='IfcQuantityArea')"
And the variable "quantity" is "{ifc}.by_type('IfcQuantityArea')[0].id()"
And I press "bim.enable_editing_cost_item_quantity(physical_quantity={quantity})"
When I press "bim.disable_editing_cost_item_quantity"
Then nothing happens
Scenario: Edit cost item quantity
Given an empty IFC project
And I press "bim.add_cost_schedule"
And the variable "cost_schedule" is "{ifc}.by_type('IfcCostSchedule')[0].id()"
And I press "bim.enable_editing_cost_items(cost_schedule={cost_schedule})"
And I press "bim.add_summary_cost_item(cost_schedule={cost_schedule})"
And the variable "cost_item" is "{ifc}.by_type('IfcCostItem')[0].id()"
And I press "bim.enable_editing_cost_item_quantities(cost_item={cost_item})"
And I press "bim.add_cost_item_quantity(cost_item={cost_item}, ifc_class='IfcQuantityArea')"
And the variable "quantity" is "{ifc}.by_type('IfcQuantityArea')[0].id()"
And I press "bim.enable_editing_cost_item_quantity(physical_quantity={quantity})"
And I set "scene.BIMCostProperties.quantity_attributes[2].float_value" to "3"
When I press "bim.edit_cost_item_quantity(physical_quantity={quantity})"
Then nothing happens
Scenario: Enable editing cost item quantity
Given an empty IFC project
And I press "bim.add_cost_schedule"
And the variable "cost_schedule" is "{ifc}.by_type('IfcCostSchedule')[0].id()"
And I press "bim.enable_editing_cost_items(cost_schedule={cost_schedule})"
And I press "bim.add_summary_cost_item(cost_schedule={cost_schedule})"
And the variable "cost_item" is "{ifc}.by_type('IfcCostItem')[0].id()"
When I press "bim.enable_editing_cost_item_values(cost_item={cost_item})"
Then nothing happens
Scenario: Add cost value - fixed
Given an empty IFC project
And I press "bim.add_cost_schedule"
And the variable "cost_schedule" is "{ifc}.by_type('IfcCostSchedule')[0].id()"
And I press "bim.enable_editing_cost_items(cost_schedule={cost_schedule})"
And I press "bim.add_summary_cost_item(cost_schedule={cost_schedule})"
And the variable "cost_item" is "{ifc}.by_type('IfcCostItem')[0].id()"
And I press "bim.enable_editing_cost_item_values(cost_item={cost_item})"
And I set "scene.BIMCostProperties.cost_types" to "FIXED"
When I press "bim.add_cost_value(parent={cost_item}, cost_type='FIXED')"
Then nothing happens
Scenario: Enable editing cost item value
Given an empty IFC project
And I press "bim.add_cost_schedule"
And the variable "cost_schedule" is "{ifc}.by_type('IfcCostSchedule')[0].id()"
And I press "bim.enable_editing_cost_items(cost_schedule={cost_schedule})"
And I press "bim.add_summary_cost_item(cost_schedule={cost_schedule})"
And the variable "cost_item" is "{ifc}.by_type('IfcCostItem')[0].id()"
And I press "bim.enable_editing_cost_item_values(cost_item={cost_item})"
And I set "scene.BIMCostProperties.cost_types" to "FIXED"
And I press "bim.add_cost_value(parent={cost_item}, cost_type='FIXED')"
And the variable "cost_value" is "{ifc}.by_type('IfcCostValue')[0].id()"
When I press "bim.enable_editing_cost_item_value(cost_value={cost_value})"
Then nothing happens
Scenario: Disable editing cost item value
Given an empty IFC project
And I press "bim.add_cost_schedule"
And the variable "cost_schedule" is "{ifc}.by_type('IfcCostSchedule')[0].id()"
And I press "bim.enable_editing_cost_items(cost_schedule={cost_schedule})"
And I press "bim.add_summary_cost_item(cost_schedule={cost_schedule})"
And the variable "cost_item" is "{ifc}.by_type('IfcCostItem')[0].id()"
And I press "bim.enable_editing_cost_item_values(cost_item={cost_item})"
And I set "scene.BIMCostProperties.cost_types" to "FIXED"
And I press "bim.add_cost_value(parent={cost_item}, cost_type='FIXED')"
And the variable "cost_value" is "{ifc}.by_type('IfcCostValue')[0].id()"
And I press "bim.enable_editing_cost_item_value(cost_value={cost_value})"
When I press "bim.disable_editing_cost_item_value"
Then nothing happens
Scenario: Edit cost item value
Given an empty IFC project
And I press "bim.add_cost_schedule"
And the variable "cost_schedule" is "{ifc}.by_type('IfcCostSchedule')[0].id()"
And I press "bim.enable_editing_cost_items(cost_schedule={cost_schedule})"
And I press "bim.add_summary_cost_item(cost_schedule={cost_schedule})"
And the variable "cost_item" is "{ifc}.by_type('IfcCostItem')[0].id()"
And I press "bim.enable_editing_cost_item_values(cost_item={cost_item})"
And I set "scene.BIMCostProperties.cost_types" to "FIXED"
And I press "bim.add_cost_value(parent={cost_item}, cost_type='FIXED')"
And the variable "cost_value" is "{ifc}.by_type('IfcCostValue')[0].id()"
And I press "bim.enable_editing_cost_item_value(cost_value={cost_value})"
When I press "bim.edit_cost_value(cost_value={cost_value})"
Then nothing happens
Scenario: Enable editing cost item value formula
Given an empty IFC project
And I press "bim.add_cost_schedule"
And the variable "cost_schedule" is "{ifc}.by_type('IfcCostSchedule')[0].id()"
And I press "bim.enable_editing_cost_items(cost_schedule={cost_schedule})"
And I press "bim.add_summary_cost_item(cost_schedule={cost_schedule})"
And the variable "cost_item" is "{ifc}.by_type('IfcCostItem')[0].id()"
And I press "bim.enable_editing_cost_item_values(cost_item={cost_item})"
And I set "scene.BIMCostProperties.cost_types" to "FIXED"
And I press "bim.add_cost_value(parent={cost_item}, cost_type='FIXED')"
And the variable "cost_value" is "{ifc}.by_type('IfcCostValue')[0].id()"
When I press "bim.enable_editing_cost_item_value_formula(cost_value={cost_value})"
Then nothing happens
Scenario: Edit cost item value formula
Given an empty IFC project
And I press "bim.add_cost_schedule"
And the variable "cost_schedule" is "{ifc}.by_type('IfcCostSchedule')[0].id()"
And I press "bim.enable_editing_cost_items(cost_schedule={cost_schedule})"
And I press "bim.add_summary_cost_item(cost_schedule={cost_schedule})"
And the variable "cost_item" is "{ifc}.by_type('IfcCostItem')[0].id()"
And I press "bim.enable_editing_cost_item_values(cost_item={cost_item})"
And I set "scene.BIMCostProperties.cost_types" to "FIXED"
And I press "bim.add_cost_value(parent={cost_item}, cost_type='FIXED')"
And the variable "cost_value" is "{ifc}.by_type('IfcCostValue')[0].id()"
And I press "bim.enable_editing_cost_item_value_formula(cost_value={cost_value})"
And I set "scene.BIMCostProperties.cost_value_formula" to "3 + 2"
When I press "bim.edit_cost_value_formula(cost_value={cost_value})"
Then nothing happens
Scenario: Add cost column
Given an empty IFC project
And I press "bim.add_cost_schedule"
And I set "scene.BIMCostProperties.should_show_column_ui" to "True"
And I set "scene.BIMCostProperties.cost_column" to "Foobar"
When I press "bim.add_cost_column(name='Foobar')"
Then nothing happens
Scenario: Remove cost column
Given an empty IFC project
And I press "bim.add_cost_schedule"
And I set "scene.BIMCostProperties.should_show_column_ui" to "True"
And I set "scene.BIMCostProperties.cost_column" to "Foobar"
And I press "bim.add_cost_column(name='Foobar')"
When I press "bim.remove_cost_column(name='Foobar')"
Then nothing happens
Scenario: Assign cost item quantity - count based
Given an empty IFC project
And I press "bim.add_cost_schedule"
And the variable "cost_schedule" is "{ifc}.by_type('IfcCostSchedule')[0].id()"
And I press "bim.enable_editing_cost_items(cost_schedule={cost_schedule})"
And I press "bim.add_summary_cost_item(cost_schedule={cost_schedule})"
And the variable "cost_item" is "{ifc}.by_type('IfcCostItem')[0].id()"
And I add a cube
And the object "Cube" is selected
And I set "scene.BIMRootProperties.ifc_class" to "IfcWall"
And I press "bim.assign_class"
When I press "bim.assign_cost_item_quantity(cost_item={cost_item}, related_object_type='PRODUCT', prop_name='')"
Then nothing happens
Scenario: Assign cost item quantity - quantity based
Given an empty IFC project
And I press "bim.add_cost_schedule"
And the variable "cost_schedule" is "{ifc}.by_type('IfcCostSchedule')[0].id()"
And I press "bim.enable_editing_cost_items(cost_schedule={cost_schedule})"
And I press "bim.add_summary_cost_item(cost_schedule={cost_schedule})"
And the variable "cost_item" is "{ifc}.by_type('IfcCostItem')[0].id()"
And I add a cube
And the object "Cube" is selected
And I set "scene.BIMRootProperties.ifc_class" to "IfcWall"
And I press "bim.assign_class"
And the object "IfcWall/Cube" is selected
And I press "bim.add_qto(obj='IfcWall/Cube', obj_type='Object')"
And I press "bim.calculate_all_quantities"
When I press "bim.assign_cost_item_quantity(cost_item={cost_item}, related_object_type='PRODUCT', prop_name='NetVolume')"
Then nothing happens
Scenario: Unassign cost item quantity - selection based
Given an empty IFC project
And I press "bim.add_cost_schedule"
And the variable "cost_schedule" is "{ifc}.by_type('IfcCostSchedule')[0].id()"
And I press "bim.enable_editing_cost_items(cost_schedule={cost_schedule})"
And I press "bim.add_summary_cost_item(cost_schedule={cost_schedule})"
And the variable "cost_item" is "{ifc}.by_type('IfcCostItem')[0].id()"
And I add a cube
And the object "Cube" is selected
And I set "scene.BIMRootProperties.ifc_class" to "IfcWall"
And I press "bim.assign_class"
And the object "IfcWall/Cube" is selected
And I press "bim.assign_cost_item_quantity(cost_item={cost_item}, related_object_type='PRODUCT', prop_name='')"
When I press "bim.unassign_cost_item_quantity(cost_item={cost_item}, related_object=0)"
Then nothing happens
Scenario: Unassign cost item quantity - explicit object
Given an empty IFC project
And I press "bim.add_cost_schedule"
And the variable "cost_schedule" is "{ifc}.by_type('IfcCostSchedule')[0].id()"
And I press "bim.enable_editing_cost_items(cost_schedule={cost_schedule})"
And I press "bim.add_summary_cost_item(cost_schedule={cost_schedule})"
And the variable "cost_item" is "{ifc}.by_type('IfcCostItem')[0].id()"
And I add a cube
And the object "Cube" is selected
And I set "scene.BIMRootProperties.ifc_class" to "IfcWall"
And I press "bim.assign_class"
And the object "IfcWall/Cube" is selected
And I press "bim.assign_cost_item_quantity(cost_item={cost_item}, related_object_type='PRODUCT', prop_name='')"
And the variable "wall" is "{ifc}.by_type('IfcWall')[0].id()"
When I press "bim.unassign_cost_item_quantity(cost_item={cost_item}, related_object={wall})"
Then nothing happens
Scenario: Select cost item products
Given an empty IFC project
And I press "bim.add_cost_schedule"
And the variable "cost_schedule" is "{ifc}.by_type('IfcCostSchedule')[0].id()"
And I press "bim.enable_editing_cost_items(cost_schedule={cost_schedule})"
And I press "bim.add_summary_cost_item(cost_schedule={cost_schedule})"
And the variable "cost_item" is "{ifc}.by_type('IfcCostItem')[0].id()"
And I add a cube
And the object "Cube" is selected
And I set "scene.BIMRootProperties.ifc_class" to "IfcWall"
And I press "bim.assign_class"
And the object "IfcWall/Cube" is selected
And I press "bim.assign_cost_item_quantity(cost_item={cost_item}, related_object_type='PRODUCT', prop_name='')"
When I press "bim.select_cost_item_products(cost_item={cost_item})"
Then nothing happens