Fix bug with incorrect MS Project XML working day imports
This commit is contained in:
@@ -202,6 +202,15 @@ class MSP2Ifc:
|
||||
self.create_task(self.tasks[subtask_id], parent_task=task)
|
||||
|
||||
def process_working_week(self, week, calendar):
|
||||
day_map = {
|
||||
"1": 7, # Sunday
|
||||
"2": 1, # Monday
|
||||
"3": 2, # Tuesday
|
||||
"4": 3, # Wednesday
|
||||
"5": 4, # Thursday
|
||||
"6": 5, # Friday
|
||||
"7": 6, # Saturday
|
||||
}
|
||||
for day in week:
|
||||
if day["ifc"]:
|
||||
continue
|
||||
@@ -210,12 +219,12 @@ class MSP2Ifc:
|
||||
"sequence.add_work_time", self.file, work_calendar=calendar, time_type="WorkingTimes"
|
||||
)
|
||||
|
||||
weekday_component = [int(day["DayType"])]
|
||||
weekday_component = [day_map[day["DayType"]]]
|
||||
for day2 in week:
|
||||
if day["DayType"] == day2["DayType"]:
|
||||
continue
|
||||
if day["WorkingTimes"] == day2["WorkingTimes"]:
|
||||
weekday_component.append(int(day2["DayType"]))
|
||||
weekday_component.append(day_map[day2["DayType"]])
|
||||
# Don't process the next day, as we can group it
|
||||
day2["ifc"] = day["ifc"]
|
||||
|
||||
|
||||